Project Updates

LIGHTHOUSE VILLA SITE PROGRESS REPORT

Activities for the week of July 28th to August 1st:

Site work:

Complete install of water line along Sundry Road

Excavate for onsite fire water tanks

 

South Wing:

Continue installation of roof insulation and strapping

Complete connection of HVAC wall caps

Continue HVAC tie-ins to ERVs

Insulate and poly all exterior walls

Begin installation of suite showers

Complete corridor electrical rough-ins

 

North Wing:

Continue install of roof insulation and strapping

Continue electrical Rough in Continue HVAC rough in

Complete plumbing rough in

Complete install of vinyl windows

 

Activities for the week of July 7th to July 11th:

Site work:

Installing hydro PMT pad

Backfilling hydro trench

Tentative installation of hydro and Telus pilasters

South Wing:

Terminating electrical at boxes

Complete attic insulation

Complete plumbing rough ins

Truss inspection

Install vinyl doors

Install windows and door flashings

Continue siding install

 

North Wing:

Prerock to continue

Installation of roof membrane to continue

Building wrap to commence

Plumbing rough-ins to continue

Truss inspection

Activities for the week of June 9 – 13th:

  • South Wing: Water line and fire suppression rough in’s
  • South Wing: Building wrap and roof installations go in
  • North Wing: Truss Installation and roof sheeting
  • North Wing: plumbing rough in’s

Activities for the week of May 12th to May 16th:

  • Completion of South Roof diaphragm
  • Roof framing inspection
  • Standing North wing walls
  • Begin installation of roofing membrane

Activities for the week of April 21st to April 25th

  • Continue installation of roof trusses, and sheathing (Simcott)
  • Continue remediation of South Wing prefabricated wall deficiencies (Atlas)
  • Begin installation of storm system: Catch basins, manholes and pipe (ITD)
  • Tentative pouring of Electrical/Mechanical Room (SCL/Simcott)
  • Begin plumbing rough-in of South Wing units (West Bay)

Activities for the week of March 22 – April 11th

  • Continue backfill of Central building area
  • Begin framing of South wing walls
  • Continue framing of South wing walls
  • Back fill of North wing units

Activities for the week of March 17th to March 21st:

    • Installation of South wing underslab poly and XPS
    • Rebar installation in South wing slab
    • Begin underslab plumbing in Central and North wing suites
    • Begin wall layouts for South wing framing
    • Tentative wall panel delivery and slab pour

Activities March 10 – 17th

  • Under Slab Plumbing and electrical rough in of south building
  • Concrete pour of North wing and building center foundation walls
  • Stripping form-work on North wing and building center foundation walls
  • Tentative damp-proofing of North wing and building center exterior foundation walls

Activities Week 16 Feb 15 – 21

  • Installation of Perimeter drain around the South wing of the building
  • Rough-in of main Sanitary lines in the south wing corridor
  • Continuation of concrete formwork
  • Foundation walls for the South wing
  • Footings for the North wing Tentative (weather dependent) start of Septic area testing

Activities Week 15  Feb 7 – 14th

Pour and strip South wing footings Form and reinforce

North wing footings and south wing walls

Complete installation of septic field testing apparatus

 

Activities for Week 11 & 12  Jan 19th to Jan 29th

Completion of excavating foundation

Installation of temporary culvert

Continue clearing of parking lot

C

Excavation of parking lot to begin

Excavation of building site to continue

Removal of danger trees from East, South and West perimeters of property

Layout of building footings and under-slab work

Activities for Week #9-10  Dec 23rd to Jan 10th

  • Log removal completed
  • Brush and stump removal in progress
  • Installation of culvert at North end of Pitt Rd.

 

Activities for Week #6-#8  Nov 30 to Dec 22:

  • Construction of Pitt Rd
  • Installation of culverts at North and South ends of Pitt Road
  • Excavation of ditch along West side of Pitt Road

Activities for Week #5 Nov 25 – 29:

  • Mulching of stumps to begin
  • Preparation of road works to begin
  • Continued maintenance of water filtration in runoff trenches

Week #4 Nov 18 – 22:

  • All trees have been cut and site has been grubbed
  • Mulching of the stumps and tree debris will start
  • Pitt road build to start