Project Updates

LIGHTHOUSE VILLA SITE PROGRESS REPORT

Activities for Week #9-10  Dec 23rd to Jan 10th

  • Log removal completed
  • Brush and stump removal in progress
  • Installation of culvert at North end of Pitt Rd.

 

Activities for Week #6-#8  Nov 30 to Dec 22:

  • Construction of Pitt Rd
  • Installation of culverts at North and South ends of Pitt Road
  • Excavation of ditch along West side of Pitt Road

Activities for Week #5 Nov 25 – 29:

  • Mulching of stumps to begin
  • Preparation of road works to begin
  • Continued maintenance of water filtration in runoff trenches

Week #4 Nov 18 – 22:

  • All trees have been cut and site has been grubbed
  • Mulching of the stumps and tree debris will start
  • Pitt road build to start

The architect, landscape design and engineers touring the Lighthouse Villa site