LIGHTHOUSE VILLA SITE PROGRESS REPORT
Activities for Week #9-10 Dec 23rd to Jan 10th
- Log removal completed
- Brush and stump removal in progress
- Installation of culvert at North end of Pitt Rd.
Activities for Week #6-#8 Nov 30 to Dec 22:
- Construction of Pitt Rd
- Installation of culverts at North and South ends of Pitt Road
- Excavation of ditch along West side of Pitt Road
Activities for Week #5 Nov 25 – 29:
- Mulching of stumps to begin
- Preparation of road works to begin
- Continued maintenance of water filtration in runoff trenches
Week #4 Nov 18 – 22:
- All trees have been cut and site has been grubbed
- Mulching of the stumps and tree debris will start
- Pitt road build to start