LIGHTHOUSE VILLA SITE PROGRESS REPORT
Activities for Week 11 & 12 Jan 19th to Jan 29th
Completion of excavating foundation
Installation of temporary culvert
Continue clearing of parking lot
Excavation of parking lot to begin
Excavation of building site to continue
Removal of danger trees from East, South and West perimeters of property
Layout of building footings and under-slab work
Activities for Week #9-10 Dec 23rd to Jan 10th
- Log removal completed
- Brush and stump removal in progress
- Installation of culvert at North end of Pitt Rd.
Activities for Week #6-#8 Nov 30 to Dec 22:
- Construction of Pitt Rd
- Installation of culverts at North and South ends of Pitt Road
- Excavation of ditch along West side of Pitt Road
Activities for Week #5 Nov 25 – 29:
- Mulching of stumps to begin
- Preparation of road works to begin
- Continued maintenance of water filtration in runoff trenches
Week #4 Nov 18 – 22:
- All trees have been cut and site has been grubbed
- Mulching of the stumps and tree debris will start
- Pitt road build to start
You must be logged in to post a comment.