LIGHTHOUSE VILLA SITE PROGRESS REPORT
Activities March 10 – 17th
- Under Slab Plumbing and electrical rough in of south building
- Concrete pour of North wing and building center foundation walls
- Stripping form-work on North wing and building center foundation walls
- Tentative damp-proofing of North wing and building center exterior foundation walls
Activities Week 16 Feb 15 – 21
- Installation of Perimeter drain around the South wing of the building
- Rough-in of main Sanitary lines in the south wing corridor
- Continuation of concrete formwork
- Foundation walls for the South wing
- Footings for the North wing Tentative (weather dependent) start of Septic area testing
Activities Week 15 Feb 7 – 14th
Pour and strip South wing footings Form and reinforce
North wing footings and south wing walls
Complete installation of septic field testing apparatus
Activities for Week 11 & 12 Jan 19th to Jan 29th
Completion of excavating foundation
Installation of temporary culvert
Continue clearing of parking lot
Excavation of parking lot to begin
Excavation of building site to continue
Removal of danger trees from East, South and West perimeters of property
Layout of building footings and under-slab work
Activities for Week #9-10 Dec 23rd to Jan 10th
- Log removal completed
- Brush and stump removal in progress
- Installation of culvert at North end of Pitt Rd.
Activities for Week #6-#8 Nov 30 to Dec 22:
- Construction of Pitt Rd
- Installation of culverts at North and South ends of Pitt Road
- Excavation of ditch along West side of Pitt Road
Activities for Week #5 Nov 25 – 29:
- Mulching of stumps to begin
- Preparation of road works to begin
- Continued maintenance of water filtration in runoff trenches
Week #4 Nov 18 – 22:
- All trees have been cut and site has been grubbed
- Mulching of the stumps and tree debris will start
- Pitt road build to start
You must be logged in to post a comment.